A small plan can fail because one untested assumption quietly became a fact. You might assume a room is available, a file can be exported, or a friend owns the equipment you need. An assumption log makes that uncertainty visible before you spend time or commit to a date. It can fit on one notebook page.
Write assumptions as checkable statements
Replace “the venue should be fine” with “the venue has an available table measuring at least six feet long on the event date.” The second statement gives you something to verify. Keep an assumption separate from a preference: wanting a Saturday appointment does not mean Saturday appointments are offered.
Use these fields: assumption; why it matters; evidence currently available; person or source to check; check-by date; result; affected decision. Add only uncertainties that could change the next step. Recording every imaginable unknown makes the page difficult to maintain.
Assumption: the existing desk fits through the office doorway. Why it matters: moving day depends on using that desk. Current evidence: a photograph, but no measurements. Check: measure the desk and the actual route, including turns. Check by: before arranging transport. Result: pending. Affected decision: move the desk assembled, disassemble it according to its instructions, or choose another arrangement.
Notice that “pending” is a useful result. It prevents an unchecked statement from being treated as confirmed. If you measure only the doorway and forget the narrow hallway turn, the assumption is still only partly tested.
Choose the next check by consequence
Start with assumptions that could make the plan unworkable or force expensive rework. A missing access permission may matter more than an undecided label color. For each check, ask what you would do differently if the assumption proved false. If the answer is “nothing,” it probably does not need a place in this log.
Close the loop when evidence arrives
Record what you observed and when. “Alex confirmed by email on Tuesday” is more useful than “sorted.” Mark the assumption confirmed, disproved, or still uncertain, and update the affected task. Confirmation can expire: a room available today might be booked later. Note when a fresh check is needed rather than treating one answer as permanent.
Do not erase disproved assumptions. Keeping the old statement and the revised plan explains why the project changed. Review the log before a purchase, booking, or handover, when uncertainty is most likely to become a commitment.
Connect any blocked work to a task dependency list so the check happens before the dependent task begins.